Wastewater Project Advances with Contract 6 Bid and Revised Timeline
Water Resources Advisory Committee · Meeting of February 2, 2026
Yarmouth's $207 million wastewater project extends completion to January 2028. The Water Resources Advisory Committee received updates on the Phase 1 initiative, with the main Water Resource Recovery Facility construction now pushed five months past the original September 2027 target due to weather delays. Contract 1, awarded to CH Nickerson for $97.55 million, is advancing with formwork and concrete installation underway.
Robert B. Our is the apparent low bidder for Contract 6 at $19.3 million. Revoli Construction, halted after a fatal trench collapse on November 18, 2025, is resuming work under newly mandated full-time safety consultant oversight required by the Select Board.
In the full story:
- The complete report — 261 words
Source: the Water Resources Advisory Committee meeting of February 2, 2026, reported from the official video recording and transcript.
Keep reading with a 30-day free trial
Subscribe to Yarmouth News to keep reading this post and get 30 days of free access to the full post archives.
Starting a trial requires a payment method. After 30 free days your subscription begins at the price shown at checkout and renews automatically until you cancel. You can cancel anytime from your account. Subscription terms
A subscription gets you:
- Subscriber-only posts and full archive
- Post comments and join the community
- 24x7 access to local news